A major food export enterprise in Hai Duong, Vietnam required an immediate fit-out of a 2,800 m² facility conforming to international HACCP, ISO 22000, and US FDA environmental standards. The facility required 3 strict environmental zones: raw material prep (quasi-clean), continuous baking & cooling (Class 100,000 / ISO 8), and sterile inner packaging (Class 10,000 / ISO 7).
The Operational Bottleneck: Local Vietnamese engineering contractors quoted 6+ months for imported equipment with a 35% broker markup, but lacked in-house HVAC balancing expertise to guarantee positive differential pressure cascades (+15 Pa) against tropical high-humidity exterior air.
BESTCLEAN's Dual-Engine Solution: All core equipment (air showers, pass boxes, AHU coils, doors, panels) was pre-fabricated in our Zhangzhou mother plant in 18 days, shipped via Xiamen Port direct to Haiphong Port (5 days ocean freight), and assembled on-site under 2 senior dispatched BESTCLEAN project directors.
All photographs captured on-site during installation and final validation handover:
Airtight cleanroom corridor separating baking and cooling lines. Flush double-glazed viewing windows with silica desiccant to withstand tropical humidity.
Automated conveyor line operated under H13 ceiling HEPA laminar flow diffusers with constant positive pressure prevent airborne microbe ingress.
High-frequency forklift and hand-truck transfer portal fitted with heavy-duty SUS304 double-swing impact doors and blue epoxy anti-slip floor.
Integrated airlock entrance pairing a single-person automatic air shower with a motorized roll-up cargo airlock for complete cross-contamination defense.
Pre-entry gowning station featuring hands-free sensor SUS304 sinks, knee-operated soap dispensers, and automated high-speed hand dryers.
Dedicated rooftop mechanical room housing modular AHU units with DX condensing sets delivering 22±2°C temperature and 50±5% RH year-round.
| System / Category | Delivered Specification & Equipment Model | Quantity | Fabrication & Verification Protocol |
|---|---|---|---|
| Envelope Wall Panels | 50mm Rockwool Sandwich Panels (0.5mm PPGI skins, 120 kg/m³ core) | 4,200 m² | Class A fire rating, ISO 14644 tongue-and-groove joint |
| Cleanroom Doors & Windows | SUS304 airtight flush single/double doors + flush double-glazed windows | 48 sets doors / 62 windows | Automatic drop-seal sweeps, 3A desiccant spacers |
| Personnel Air Showers | BJ1400-D-QP-2 Two-person double blow SUS304 air showers | 4 units | 100% Testo anemometer calibrated to 22.5 m/s |
| Cargo Air Shower Tunnel | BJ3000 Cargo Air Shower with high-speed PVC roll-up doors | 2 suites | Infrared sensor automated opening, 36 nozzles |
| Purification AHUs | B-JZP15 Modular Cleanroom Air Handling Units (15,000 m³/h, 900 Pa) | 6 sets | Direct-expansion DX scroll condensing units, primary+medium filters |
| HEPA Terminal Outlets | BJ-15IB Ceiling Diffusers with H13 Mini-Pleat Filters (99.99% @ 0.3µm) | 180 sets | Factory DOP aerosol leak scanned before packing |
Instead of hiring an expensive international construction firm or leaving local crews without guidance, BESTCLEAN dispatched 2 seasoned cleanroom project directors (1 HVAC commissioning specialist + 1 structural panel supervisor) to Hai Duong for 38 consecutive days: